Spare Unit of Pol-Kaleh III Gas Compressor Facilities Put into Operation in Absence of Experts of Turbine Manufacturing Plant

Following operation of spare units of gas compressor facilities of Takab and Pataveh III, the spare unit of gas compressor facilities of Pol-Kaleh III was put into operation this year.

It should be noted that due to the absence of the experts from Siemens Company, all the functioning operations and the 72-hour test at Pol-Kaleh III facilities were entirely performed by the executives of the project and those involved in Zone 2 of gas transfer operations.